Do I need a permit for a deck, fence or shed in Windsor, Ontario?

Windsor, Ontario, Canada

In Windsor a deck needs a building permit, most fences do not, and a shed needs one if it is over 10 square metres.

Key information

In Windsor, decks need a building permit, fences (other than masonry or concrete) do not, and sheds need one only if they are over 10 square metres. Apply online and have the permit before work starts.

Exterior of the modern Windsor City Hall building with trees in front.
Windsor City Hall in Windsor, Ontario, July 2025. Photo: Chris Woodrich, Wikimedia Commons, CC BY-SA 4.0.
On this page

At a glance

Windsor permits for common backyard projects
ProjectPermit needed?
DeckYes
Fence (not masonry or concrete)No
Masonry or concrete fenceYes, it is not exempt
Shed or detached accessory structure under 10 m²No
Freestanding structure over 10 m²Yes
PoolYes
Landscaping, painting, eavestroughsNo

Sources: Building Permits | City of Windsor

When do I need a permit?

The city says projects such as decks, porches, sunrooms, carports, garages, pools and additions need a building permit. Freestanding structures over 10 square metres (108 square feet) also need one.

No permit is needed for fences other than masonry or concrete, detached accessory structures under 10 square metres, landscaping, painting and eavestroughs. Zoning rules still apply, such as Zoning By-law 8600, so check them for your lot.

Sources: Building Permits | City of Windsor

How do I apply?

  1. Check the Ontario Building Code and the Zoning By-law for your address.
  2. Prepare drawings that meet the city's Schedule 2.1 and 2.2 lists.
  3. Apply through the city's online e-permitting system. The owner can apply or can authorize a contractor or designer.
  4. Wait for the permit. The owner must have it before work starts.
  5. Book the required inspections during construction.

Sources: Building Permits | City of Windsor

What are the time limits and risks?

Work must start within 6 months of the permit being issued. If work stops for more than 1 year, the permit may be revoked.

Building without a permit can mean costly repairs, removal of work, a higher application fee, or legal action. The city page lists no fee amounts, so ask the Building Division.

Sources: Building Permits | City of Windsor

Questions and answers

Do I need a permit for a deck in Windsor?

Yes. Decks are listed as projects that need a building permit.

Source: Building Permits | City of Windsor

Do I need a permit for a fence?

No, unless it is masonry or concrete.

Source: Building Permits | City of Windsor

Do I need a permit for a shed?

Only if it is over 10 square metres. Smaller detached structures are exempt.

Source: Building Permits | City of Windsor

Does a pool need a permit?

Yes. Pools are on the city's list of projects that need a permit.

Source: Building Permits | City of Windsor

Can a contractor apply for me?

Yes. The owner can authorize a contractor or designer to apply.

Source: Building Permits | City of Windsor

Where do I apply?

Through the city's online e-permitting system, linked from the Building page.

Source: Building Permits | City of Windsor

When must work start?

Within 6 months of the permit being issued.

Source: Building Permits | City of Windsor

Is demolition covered?

Demolishing a building over 10 square metres generally needs a permit, except farm buildings.

Source: Building Permits | City of Windsor

Who answers zoning questions?

The Planning Department at 519-255-6543 or planningdept@citywindsor.ca.

Source: Building Permits | City of Windsor

Who do I call about permits?

The Building Division at 519-255-6267 or buildingdept@citywindsor.ca.

Source: Building Permits | City of Windsor